Central WWTP Capacity Improvements and CSO Reduction

The Central Wastewater Treatment Plant (CWWTP) Capacity Improvements and CSO Reduction project will reduce the overflow frequency and volume from the Kerrigan CSO by increasing both the wet weather treatment capacity of the CWWTP and the overall capacity of the Central Pumping Station. The project will also add on-site CSO storage and equalization to assist in managing the dramatic flow rate increases from the combined sewer system during intense rainfall events.

The CWWTP, the largest treatment plant in Nashville, is located in the Germantown and Salemtown area near downtown and was originally constructed in 1958. It has previously had four major expansions. Peak plant capacity is currently 330 million gallons per day (mgd), and the project’s planned improvements will expand it to over 400 MGD. The $400M project is being delivered through a Construction Manager at Risk (CMAR) approach.

Improvements include, but are not limited to: Central Pump Station upgrades, new switchgear building, new 440 mgd headworks facility, large diameter conveyance piping, primary settling tank improvements, Intermediate Pump Station upgrades, conversion to fine bubble aeration, new blowers, Return Activated Sludge (RAS) system improvements, conversion of existing chlorine contact tanks to new ultraviolet disinfection facility, plant water system improvements, biosolids facility improvements, new waste gas flare, excess flow treatment unit modifications, civil and landscaping improvements, and primary power system improvements.

Project Details

Project Type: Other
Project Area Map: View map
Metro Project #: 14SC0153
Council District(s): 19
Sewer basin: Central
Designer: Brown and Caldwell, Hazen and Sawyer
Contractor: Brasfield & Gorrie - CMAR

Project Timeline

Phase Start Finish
Design September 2015 May 2020
Permitting/Bid/Award August 2016 September 2020
Construction July 2020 August 2024

Project Photos

Initial demolition site work for headworks facility, Spring/Summer 2020

Construction continues on headworks facility, Updated December 1, 2021