Vandiver Pump Station Upgrades

To convey additional flows and remediate nearby sanitary sewer overflows, this project includes the construction of a new pump station with greater capacity and the upgrade of one of the two associated force mains.

Project Details

Project Type: Pump Station
Project Area Map: View map
Metro Project #: 11-SC-0109
Council District(s): 9
Sewer basin: Dry Creek
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design June 2021 July 2022
Permitting/Bid/Award July 2022 July 2024
Construction July 2024 October 2025