Sewer Rehabilitation Begins in Bordeaux and Metro Center

Construction activities began in December 2023 for the Annual Rehabilitation - Bordeaux and Metro Center project. This project was identified to reduce wet-weather flows within the sewer system by addressing observed sources of infiltration and inflow through sewer rehabilitation. It also considers nearby sewers for inclusion in the project based on their condition, the likelihood of water migration to adjacent sewers, and the impact to customers. Work consists of the rehabilitation of approximately 21,000 linear feet of existing sewer lines by cured-in-place-pipe lining, service replacements by excavation, trenchless service renewals, manhole rehabilitation, and other miscellaneous sewer-related work. 

Project page : Annual Rehabilitation - Bordeaux and Metro Center

Kimberly Martin