Tuckahoe-Nesbitt Rehabilitation

This project was developed to renew aging infrastructure and address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 52,500 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11-SC-144B
Council District(s): 3, 8
Sewer basin: Whites Creek
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design December 2022 June 2023
Permitting/Bid/Award June 2023 October 2023
Construction October 2023 January 2025