Towne Village Pump Station Upgrades

To convey additional flows and remediate nearby sanitary sewer overflows, this project includes the construction of a new pump station with greater capacity.

Project Details

Project Type: Pump Station
Project Area Map: View Map
Metro Project #: 22SC0132
Council District(s): 29
Sewer basin: Central
Designer: Brown & Caldwell
Contractor: TBD

Project Timeline

Phase Start Finish
Design June 2024 May 2026
Permitting/Bid/Award January 2025 December 2026
Construction Deember 2026 February 2028