Towne Village Pump Station Upgrades

To convey additional flows and remediate nearby sanitary sewer overflows, this project includes the construction of a new pump station with greater capacity, and the upgrade and reroute of the associated force main.

Project Details

Project Type: Pump Station
Project Area Map: View map
Metro Project #: 22SC0132
Council District(s): 33
Sewer basin: Dry Creek
Designer: Brown & Caldwell
Contractor: TBD

Project Timeline

Phase Start Finish
Design June 2024 September 2025
Permitting/Bid/Award September 2026 December 2026
Construction Deember 2026 December 2027