Smith Springs Rehabilitation - Area 2 - Castlegate

Completed October 2018

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 58,800 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11-SC-120B
Council District(s): 29, 33
Sewer basin: Central
Designer: Civil Infrastructure Associates, LLC
Contractor: SBW Constructors, LLC

Project Timeline

Phase Start Finish
Design February 2016 August 2016
Permitting/Bid/Award August 2016 January 2017
Construction January 2017 October 2018