Shelby Park Rehabilitation - Area 6 - Shelby Trunk

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 36,200 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11-SC-105F
Council District(s): 6, 7
Sewer basin: Central
Designer: Hethcoat & Davis, Inc.
Contractor: TBD

Project Timeline

Phase Start Finish
Design February 2017 October 2017
Permitting/Bid/Award April 2020 September 2020
Construction September 2020 January 2022