Richland Creek - Basswood Drive 36-Inch CIPP

This project was developed to renew aging sewer infrastructure and to address overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the rehabilitation of approximately 1,000 linear feet of gravity sewer by cured-in-place-pipe lining, service replacements by excavation, trenchless service renewals, manhole rehabilitation, and other miscellaneous sewer-related work.

The rehabilitation work will primarily occur in easements and public roadways. Construction methods will include trenchless technologies (pipe and manhole lining) to minimize excavation in streets and properties. However, some excavation will be necessary on certain streets, in existing easements, and in public rights-of-way for sewer service renewals to individual properties. Temporary piping for diversion pumping may be installed on the ground. Roadways and properties disturbed by the work will be restored to their original conditions as closely as possible in a manner that will ensure that MWS can maintain future access to the public sewer infrastructure.

Project Details

Project Type: Rehabilitation
Project Area Map: View Map
Metro Project #: 24SC127B
Council District(s): 20
Sewer basin: Whites Creek
Designer: CWNOAP
Contractor: Inliner Solutions, LLC

Project Timeline

Phase Start Finish
Design June 2025 July 2025
Permitting/Bid/Award June 2025 October 2025
Construction October 2025 January 2026