Norman Drive Pipe Improvements (GC14)

To provide increased conveyance capacity and address restrictions within the sewer system that result in overflows, approximately 4,000 linear feet of gravity sewer pipe will be replaced with larger sewers.

Project Details

Project Type: Conveyance
Project Area Map: View map
Metro Project #: 11-SC-0138
Council District(s): 8
Sewer basin: Dry Creek
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design March 2023 April 2024
Permitting/Bid/Award April 2024 October 2025
Construction October 2025 November 2026