Mill Creek Pump Station Sewer Rehabilitation
This project was developed to renew aging sewer infrastructure and to address overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation of approximately 41,700 linear feet of gravity sewer, approximately 240 manholes, and associated service laterals within Metro’s rights-of-way and easements.
Construction methods will include trenchless technologies (pipe and manhole lining) to minimize excavation in streets and properties. However, some excavation will be necessary on certain streets, in existing easements, and in public rights-of-way for sewer service renewals to individual properties. Roadways and properties disturbed by the work will be restored to their original conditions as closely as possible in a manner that will ensure that MWS can maintain future access to the public sewer infrastructure.
Project Details
| Project Type: | Rehabilitation |
| Project Area Map: | View Map |
| Metro Project #: | 26SC0125 |
| Council District(s): | 15 |
| Sewer basin: | Central |
| Designer: | TBD |
| Contractor: | TBD |
Project Timeline
| Phase | Start | Finish |
|---|---|---|
| Design | September 2026 | March 2027 |
| Permitting/Bid/Award | October 2026 | June 2027 |
| Construction | June 2027 | August 2028 |