Loves Branch Rehabilitation
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 51,900 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.
Project Details
| Project Type: | Rehabilitation |
| Project Area Map: | View map |
| Metro Project #: | 11-SC-108A |
| Council District(s): | 7, 8 |
| Sewer basin: | Day Creek |
| Designer: | Dempsey, Dilling & Associates, P.C. |
| Contractor: | Insituform Technologies, LLC |
Project Timeline
| Phase | Start | Finish |
|---|---|---|
| Design | October 2016 | June 2017 |
| Permitting/Bid/Award | June 2017 | December 2017 |
| Construction | December 2017 | April 2019 |