Joelton Sewer Force Main

To convey additional flows and remediate nearby sanitary sewer overflows, this project includes replacement of the existing 8,100 LF of 6-inch diameter force main with a new 12-inch diameter force main for the Joelton Pump Station.

Project Details

Project Type: Conveyance
Project Area Map: View Map
Metro Project #: 21SG0141
Council District(s): 1
Sewer basin: Whites Creek
Designer: MWS
Contractor: Cleary Construction, Inc.

Project Timeline

Phase Start Finish
Bid/Award June 2025 October 2025
Construction October 2025 February 2027