Holiday Travel Park Gravity Conversion
Completed August 2012
Construction of gravity sewer to eliminate the Holiday Park Pump Station.
Project Timeline
| Phase | Start | Finish |
|---|---|---|
| Design | June 2007 | August 2011 |
| Permitting/Bid/Award | September 2011 | February 2012 |
| Construction | March 2012 | August 2012 |