Highway 100 / Tyne Boulevard Pipe Improvements

To provide increased conveyance capacity and address restrictions within the sewer system that result in overflows, approximately 17,900 linear feet of gravity sewer pipe will be replaced with larger sewers.

Project Details

Project Type: Conveyance
Project Area Map: View map
Metro Project #: 11-SC-0147
Council District(s):
Sewer basin:
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design April 2023 September 2024
Permitting/Bid/Award Spetember 2024 December 2025
Construction December 2025 January 2028

Project Photos