Gibson Creek Rehabilitation - Area 2 - Forest Park Road

The Gibson Creek Rehabilitation - Area 2 - Forest Park project was developed to renew aging infrastructure and address overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation, as necessary, of approximately 31,500 linear feet of existing gravity sewer, approximately 170 manholes, and associated service laterals within Metro’s rights-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View Map
Metro Project #: 26SC0121
Council District(s): 9
Sewer basin: Dry Creek
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design July 2026 January 2027
Permitting/Bid/Award August 2026 April 2027
Construction April 2027 June 2028

Project Photos