Gibson Creek Rehabilitation - Area 1 - Dupont Avenue

Completed December 2017

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 59,500 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11-SC-0140A
Council District(s): 7, 8, 9
Sewer basin: Dry Creek
Designer: Orchard, Hiltz, & McCliment, Inc.
Contractor: Insituform Technologies, LLC

Project Timeline

Phase Start Finish
Design July 2015 April 2016
Permitting/Bid/Award April 2016 September 2016
Construction September 2016 December 2017