Dodson Chapel and McCrory Creek Study and Future Projects
This project consists of extensive flow monitoring in the winter/spring of 2022, followed by an update to the hydraulic model and an evaluation of alternatives to address the overflows. The assessment and proposed corrective actions will be summarized in a supplemental report submitted in mid 2023
Project Details
| Project Type: | Rehabilitation |
| Project Area Map: | |
| Metro Project #: | |
| Council District(s): | 11,12,13,14,15 |
| Sewer basin: | Central |
| Designer: | TBD |
| Contractor: | TBD |
Project Timeline
| Phase | Start | Finish |
|---|---|---|
| Design | December 2026 | June 2029 |
| Permitting/Bid/Award | June 2027 | June 2029 |
| Construction | December 2027 | April 2031 |
Project Photos