Cowan Street Pipe Improvements

Approximately 7,300 linear feet of gravity pipe replacement, increasing diameters ranging from 10 inches to 30 inches to a range of 12 inches to 36 inches.

Project Details

Project Type: Conveyance
Project Area Map: View map
Metro Project #: 11SC0113
Council District(s): 2, 19
Sewer basin: Central
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design October 2027 April 2028
Permitting/Bid/Award September 2028 May 2029
Construction May 2029 September 2030

Project Photos

No photos available.