Cowan Street Pipe Improvements

Approximately 7,300 linear feet of gravity pipe replacement, increasing diameters ranging from 10 inches to 30 inches to a range of 12 inches to 36 inches.

Project Details

Project Type: Conveyance
Project Area Map: View map
Metro Project #: 11-SC-0113
Council District(s): 2, 5
Sewer basin: Central
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design September 2021 March 2022
Permitting/Bid/Award March 2022 April 2023
Construction April 2023 August 2024

Project Photos

No photos available.