Cowan Street Pipe Improvements
Approximately 7,300 linear feet of gravity pipe replacement, increasing diameters ranging from 10 inches to 30 inches to a range of 12 inches to 36 inches.
Project Details
| Project Type: | Conveyance |
| Project Area Map: | View map |
| Metro Project #: | 11SC0113 |
| Council District(s): | 2, 19 |
| Sewer basin: | Central |
| Designer: | TBD |
| Contractor: | TBD |
Project Timeline
| Phase | Start | Finish |
|---|---|---|
| Design | October 2027 | April 2028 |
| Permitting/Bid/Award | September 2028 | May 2029 |
| Construction | May 2029 | September 2030 |