Berwick Trail Pump Station Upgrades

To convey additional flows and address nearby sanitary sewer overflows, this project includes the construction of a new pump station with greater capacity. Approximately 7,100 linear feet of the associated force main will be upgraded as part of the Neely’s Bend Pump Station Upgrades project to convey the additional flow from the increased capacities of the Berwick Trail Pump Station and Neely’s Bend Pump Station.

Project Details

Project Type: Pump Station
Project Area Map: View map
Metro Project #: 11-SC-0107
Council District(s): 9
Sewer basin: Dry Creek
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design March 2022 August 2022
Permitting/Bid/Award August 2022 March 2023
Construction March 2023 April 2024

Project Photos