Berwick Trail Pipe Improvements

Approximately 2,600 linear feet of gravity conveyance upgrades, increasing in diameter from 8 inches to a range of 12 inches to 18 inches.

Project Details

Project Type: Conveyance
Project Area Map: View map
Metro Project #: 11-SC-0136
Council District(s): 9
Sewer basin: Dry Creek
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design June 2022 November 2022
Permitting/Bid/Award November 2022 November 2023
Construction November 2023 2023 March 2025

Project Photos

No photos available.