28th Avenue Rehabilitation – Future Areas

This multiphase project was developed to renew aging infrastructure and address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of up to 193,000 linear feet total of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: TBD
Council District(s): 21
Sewer basin: Central
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design September 2021 June 2024
Permitting/Bid/Award April 2022 January 2023
Construction October 2022 April 2026