Henry Ford Drive Pipe Improvements

Gravity pipe replacement project of approximately 2,700 linear feet, increasing pipe diameters from 12 inches to 16 inches.

Project Details

Project Type: Conveyance
Project Area Map: View map
Metro Project #: 11-SC-0146
Council District(s): 20
Sewer basin: Whites Creek
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design July 2021 January 2022
Permitting/Bid/Award January 2022 September 2023
Construction September 2023 January 2025