Combined Sewer System and First Avenue Tunnel Rehabilitation

Rehabilitation of the existing 72-inch First Avenue Tunnel and other various combined sewer system rehabilitation, as identified.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11-SC-0129
Council District(s): 19
Sewer basin: Central
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design December 2022 June 2023
Permitting/Bid/Award June 2023 December 2023
Construction December 2023 April 2025