Tuckahoe-Nesbitt Rehabilitation

This project was developed to renew aging infrastructure and address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 52,500 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11SC144B
Council District(s): 3
Sewer basin: Whites Creek
Designer: CWN
Contractor: TBD

Project Timeline

Phase Start Finish
Design October 2023 April 2024
Permitting/Bid/Award April 2024 July 2024
Construction July 2024 May 2025