Towne Village Pump Station Upgrades
To convey additional flows and remediate nearby sanitary sewer overflows, this project includes the construction of a new pump station with greater capacity, and the upgrade and reroute of the associated force main.
Project Details
Project Type: | Pump Station |
Project Area Map: | View map |
Metro Project #: | 22SC0132 |
Council District(s): | 33 |
Sewer basin: | Dry Creek |
Designer: | Brown & Caldwell |
Contractor: | TBD |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | April 2024 | October 2024 |
Permitting/Bid/Award | December 2025 | May 2026 |
Construction | May 2026 | May 2027 |