Smith Springs Rehabilitation - Area 1 - Priest Lake Meadows

Completed March 2017

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 64,000 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11-SC-0120A
Council District(s): 29
Sewer basin: Central
Designer: ICA Engineering
Contractor: Layne Inliner, LLC

Project Timeline

Phase Start Finish
Design February 2015 October 2015
Permitting/Bid/Award October 2015 February 2016
Construction February 2016 March 2017