Shelby Park Rehabilitation - Future Areas

This multiphase project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. This project consists of the evaluation and rehabilitation (as necessary) of up to 630,000 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: TBD
Council District(s): 5, 6, 7, 8
Sewer basin: Central
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design December 2029 July 2031
Permitting/Bid/Award May 2030 October 2031
Construction September 2030 February 2033

Project Photos