Shelby Park Rehabilitation - Area 2 - Norvel Avenue

Completed February 2016

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation of approximately 57,000 linear feet of 8 to 21-inch gravity sewer, 300 associated manholes, and 700 service laterals within Metro's right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11-SC-0105B
Council District(s): 7, 8
Sewer basin: Central
Designer: GRW Engineers, Inc.
Contractor: SAK Construction, LLC

Project Timeline

Phase Start Finish
Design July 2013 January 2014
Permitting/Bid/Award January 2014 May 2014
Construction May 2014 February 2016