Long Blvd Alley Sanitary Sewer Upsize

In order to provide increased conveyance capacity and address existing restrictions within the sewer system, approximately 550 linear feet of gravity sewer pipe will be replaced with larger sewers.

Project Details

Project Type: Conveyance
Project Area Map: View Map
Metro Project #: 22SC0032
Council District(s): 21
Sewer basin: Central
Designer: CWN
Contractor: SBW Constructors LLC

Project Timeline

Phase Start Finish
Design April 2022 July 2022
Permitting/Bid/Award August 2022 October 2022
Construction October 2022 April 2023

Project Photos