Highway 100 & Tyne Boulevard - Trimble Rehabilitation

Completed January 2016

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consisted of the evaluation of approximately 63,000 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements. The resulting construction project includes the rehabilitation of approximately 33,000 linear feet of 8 to 12-inch gravity sewer, associated manholes, and service connections.

Project Details

Project Type: Rehabilitation
Project Area Map: View map
Metro Project #: 11-SC-0147A
Council District(s): 23, 34
Sewer basin: Whites Creek
Designer: Jacobs Engineering Group, Inc.
Contractor: Insituform Technologies, LLC

Project Timeline

Phase Start Finish
Design September 2013 April 2014
Permitting/Bid/Award April 2014 August 2014
Construction August 2014 January 2016

Project Photos