Driftwood Equalization Facility

Completed November 2013

This project increased the storage capacity of the existing Driftwood facility by 3.2 million gallons and corrected operational electrical defects at the site. Through these improvements, the storage facility is now able to capture the additional flow generated from most rainfall events, preventing the release of combined sewage to the Cumberland River.

Project Details

Project Type: Equalization Facility
Project Area Map: View map
Metro Project #: 11-SC-0067
Council District(s): 19
Sewer basin: Central
Designer: Smith Seckman Reid, Inc.
Contractor: Haren Construction Co. Inc

Project Timeline

Phase Start Finish
Design August 2011 April 2012
Permitting/Bid/Award April 2012 July 2012
Construction July 2012 November 2013