Night Work Begins for the 16" Water Transmission Main and Pump Station Project

Originally Published 6/2/2015

On Monday, March 2, 2015, Metro Water Services began the construction of a water main and water pumping station project with portions of work being adjacent to the Cleanwater Nashville OAP project, Lakewood Rehabilitation.

Starting May 31, 2015, night work will begin taking place for the construction of the water main portion of this project along Old Hickory Boulevard from 22nd to Hadley within the TDOT right of way. Due to traffic along Old Hickory Boulevard, TDOT restrictions require work to be completed from 7PM to 6AM. The work is expected to take approximately 2 months to complete.

For the initial project notification letter with more detail, please click here.

For more information regarding this work, please contact Metro Water Services contact Metro Water Services.

Julie Flynn