Additional updates

Washington CSO Control Facility goes online

Date added: 11-Aug-2015 09:35 AM

Washington CSO Control Facility goes onlineA major combined sewer facility providing optimization for wet weather storage, screening and control of floatables and solids went online in April of this year. In addition to providing treatment, the facility dramatically reduces the number of overflows at the Washington outfall, and reduces the volume of overflows by approximately 90 percent annually.

Constructed at a cost of approximately $17 million, it was operationally complete in time to meet the Consent Decree milestone.
[read more...]

Update on the Metro Nashville Consent Decree Program

Date added: 11-Aug-2015 09:34 AM

Update on the Metro Nashville Consent Decree ProgramOn August 6, 2012, Scott Potter and Ron Taylor of Metro Water Services provided an update on the Clean Water Nashville Overflow Abatement Program program to the Metro Council. This presentation addressed the status of the Consent Decree and planned projects included in the Long Term Control Plan for Metro Nashville Combined Sewer Overflows (Long Term Control Plan update) and the Corrective Action Plan/Engineering Report.Click here to download a copy of the presentation.
[read more...]

Driftwood Equalization Facility modifications completed, doubling facility's capacity

The Driftwood Equalization Facility, located on the eastern edge of downtown Nashville, off of Hermitage Avenue on Visco Drive, has been modified to store an additional 3.2 million gallons of combined sewage during peak rain events. This project is a means of reducing or eliminating wet weather overflows during major rain events.

By raising the concrete walls at Driftwood’s open storage facility and installing six new weir gates, CWN has doubled water detention capacity to almost 7 million gallons.

The added capacity is a significant achievement for Cumberland River water quality. Before expansion, the facility experienced an average of six combined sewer overflows (CSOs) into the Cumberland each year. The newly expanded facility is now large enough that hydraulic models project zero CSOs in a typical rainfall year. With the improvement to Driftwood and the recent elimination of CSO discharge locations at Broadway and Van Buren, Nashville has substantially reduced overflows into the Cumberland.