MWS hosts mobile workshop

Date added: 14-Dec-2015 08:18 AM

MWS hosts mobile workshopIn November 2015, Nashville was home to the National League of Cities 2015 Congress of Cities, and Metro Water Services (MWS) proudly hosted a contingent of the visiting municipal officials for a workshop about the Clean Water Nashville Overflow Abatement Program (Program).
[read more...]

Smoke testing yields clues for system repair

Date added: 26-Aug-2015 07:35 AM

Smoke testing yields clues for system repairCLEAN WATER NASHVILLE USES A VARIETY OF TECHNIQUES to assess the condition of the underground sewer system. One of those techniques, smoke testing, is a low-tech method, but can be effective at identifying potential defects in the system.
[read more...]

Natural setting shapes repair approach

Date added: 26-Aug-2015 07:33 AM

Natural setting shapes repair approachDAVIDSON COUNTY’S SURROUNDING environment is an ever-present factor in how the Clean Water Nashville Program plans construction repairs on aged and defective wastewater infrastructure.
[read more...]

East Nashville rehab projects continue in Inglewood and Jackson Park neighborhoods

Date added: 26-Aug-2015 07:31 AM

East Nashville rehab projects continue in Inglewood and Jackson Park neighborhoodsCOMPREHENSIVE SEWER SYSTEM RENEWAL throughout large areas of East Nashville and Inglewood continues with the start of the Shelby Park Rehabilitation—Area 4—Brush Hill Road project.
[read more...]

Community Engagement

Clean Water Nashville Overflow Abatement Program (CWNOAP) team leaders shared plans for renewing wastewater system infrastructure in North Nashville with over 150 area residents gathered for a February 27 community meeting hosted by Metro Council District 3 representative Brenda Haywood.

District 3, which includes Whites Creek, is one of Nashville’s largest geographic districts. Residents were briefed on current and planned wastewater projects in District3 that include the following:

  • The Annual Rehabilitation FY2014 – Whites Creek Trunk project is currently under construction and consists of rehabilitating approximately 55,800 linear feet of gravity sewer, manholes, and service laterals within the public rights-of-way. This project renews aged infrastructure and addresses downstream overflows by limiting groundwater infiltration.

  • The Brick Church Pike Pipe Improvements project consists of replacing approximately 9,800 linear feet of gravity sewer pipe with larger diameter sewer pipe. Construction is expected to begin in summer 2016 and is scheduled for completion in 2018.

  • The Ewing Creek/Brick Church Equalization Facility consists of constructing a 10.6 million gallon storage tank and an 18 million gallons per day pumping station. The new facility will provide the necessary capacity to eliminate sanitary sewer overflows. Currently in design, the project is scheduled for construction starting in 2017.

The CWNOAP recently completed the Westchester Drive Rehabilitation project, which involved rehabilitating 3,850 feet of sewer pipe along and crossing the North Fork of Ewing Creek, a tributary to Whites Creek. Cracked pipes and other defects within the system that had previously allowed ground water infiltration into the system were repaired.

Community engagement and public information is an ongoing priority of the CWNOAP. Project team leaders work closely with Metro Council representatives on a regular basis to provide residents with information about the purpose, impacts, and work schedules of upcoming projects.