Cleanwater Nashville

Metro Water Services

News

Additional updates

Community Engagement

Date added: 01-Mar-2016 08:19 AM

Community EngagementClean Water Nashville Overflow Abatement Program (CWNOAP) team leaders shared plans for renewing wastewater system infrastructure in North Nashville with over 150 area residents gathered for a February 27 community meeting hosted by Metro Council District 3 representative Brenda Haywood.
[read more...]

2015 highlights include completion of major projects

Date added: 24-Aug-2016 08:50 AM

2015 highlights include completion of major projectsDODSON CHAPEL PIPE IMPROVEMENTS PROJECT, located in Metro Council Districts 11 and 14, was completed in December 2015.

MILL CREEK/OPRYLAND EQUALIZATION FACILITY, PHASE II, increased storage capacity with the addition of a 19-million gallon, pre-stressed concrete wastewater storage tank adjacent to an existing 15-million gallon tank. The project was completed in April 2015.

COWAN RIVERSIDE REHABILITATION AREA 1—JONES AVENUE was conducted to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects.
[read more...]

Service lines connect citizens to public sewer system

Date added: 10-Feb-2016 02:23 PM

Service lines connect citizens to public sewer systemTHE CLEAN WATER NASHVILLE PROGRAM is constructing sewer rehabilitation projects to renew sewer infrastructure and reduce overflows that may lead to water quality impairments. These sewer rehabilitation projects are located throughout the county, including large projects currently under construction in Council Districts 2, 5, 7, 8 and 29.
[read more...]

MWS hosts mobile workshop

Date added: 14-Dec-2015 08:18 AM

MWS hosts mobile workshopIn November 2015, Nashville was home to the National League of Cities 2015 Congress of Cities, and Metro Water Services (MWS) proudly hosted a contingent of the visiting municipal officials for a workshop about the Clean Water Nashville Overflow Abatement Program (Program).
[read more...]

Community Engagement

Clean Water Nashville Overflow Abatement Program (CWNOAP) team leaders shared plans for renewing wastewater system infrastructure in North Nashville with over 150 area residents gathered for a February 27 community meeting hosted by Metro Council District 3 representative Brenda Haywood.

District 3, which includes Whites Creek, is one of Nashville’s largest geographic districts. Residents were briefed on current and planned wastewater projects in District3 that include the following:

  • The Annual Rehabilitation FY2014 – Whites Creek Trunk project is currently under construction and consists of rehabilitating approximately 55,800 linear feet of gravity sewer, manholes, and service laterals within the public rights-of-way. This project renews aged infrastructure and addresses downstream overflows by limiting groundwater infiltration.

  • The Brick Church Pike Pipe Improvements project consists of replacing approximately 9,800 linear feet of gravity sewer pipe with larger diameter sewer pipe. Construction is expected to begin in summer 2016 and is scheduled for completion in 2018.

  • The Ewing Creek/Brick Church Equalization Facility consists of constructing a 10.6 million gallon storage tank and an 18 million gallons per day pumping station. The new facility will provide the necessary capacity to eliminate sanitary sewer overflows. Currently in design, the project is scheduled for construction starting in 2017.

The CWNOAP recently completed the Westchester Drive Rehabilitation project, which involved rehabilitating 3,850 feet of sewer pipe along and crossing the North Fork of Ewing Creek, a tributary to Whites Creek. Cracked pipes and other defects within the system that had previously allowed ground water infiltration into the system were repaired.

Community engagement and public information is an ongoing priority of the CWNOAP. Project team leaders work closely with Metro Council representatives on a regular basis to provide residents with information about the purpose, impacts, and work schedules of upcoming projects.