Washington CSO Control Facility goes online

Date added: 11-Aug-2015 09:35 AM

Washington CSO Control Facility goes onlineA major combined sewer facility providing optimization for wet weather storage, screening and control of floatables and solids went online in April of this year. In addition to providing treatment, the facility dramatically reduces the number of overflows at the Washington outfall, and reduces the volume of overflows by approximately 90 percent annually.

Constructed at a cost of approximately $17 million, it was operationally complete in time to meet the Consent Decree milestone.
[read more...]

Update on the Metro Nashville Consent Decree Program

Date added: 11-Aug-2015 09:34 AM

Update on the Metro Nashville Consent Decree ProgramOn August 6, 2012, Scott Potter and Ron Taylor of Metro Water Services provided an update on the Clean Water Nashville Overflow Abatement Program program to the Metro Council. This presentation addressed the status of the Consent Decree and planned projects included in the Long Term Control Plan for Metro Nashville Combined Sewer Overflows (Long Term Control Plan update) and the Corrective Action Plan/Engineering Report.Click here to download a copy of the presentation.
[read more...]

Community Engagement

Clean Water Nashville Overflow Abatement Program (CWNOAP) team leaders shared plans for renewing wastewater system infrastructure in North Nashville with over 150 area residents gathered for a February 27 community meeting hosted by Metro Council District 3 representative Brenda Haywood.

District 3, which includes Whites Creek, is one of Nashville’s largest geographic districts. Residents were briefed on current and planned wastewater projects in District3 that include the following:

  • The Annual Rehabilitation FY2014 – Whites Creek Trunk project is currently under construction and consists of rehabilitating approximately 55,800 linear feet of gravity sewer, manholes, and service laterals within the public rights-of-way. This project renews aged infrastructure and addresses downstream overflows by limiting groundwater infiltration.

  • The Brick Church Pike Pipe Improvements project consists of replacing approximately 9,800 linear feet of gravity sewer pipe with larger diameter sewer pipe. Construction is expected to begin in summer 2016 and is scheduled for completion in 2018.

  • The Ewing Creek/Brick Church Equalization Facility consists of constructing a 10.6 million gallon storage tank and an 18 million gallons per day pumping station. The new facility will provide the necessary capacity to eliminate sanitary sewer overflows. Currently in design, the project is scheduled for construction starting in 2017.

The CWNOAP recently completed the Westchester Drive Rehabilitation project, which involved rehabilitating 3,850 feet of sewer pipe along and crossing the North Fork of Ewing Creek, a tributary to Whites Creek. Cracked pipes and other defects within the system that had previously allowed ground water infiltration into the system were repaired.

Community engagement and public information is an ongoing priority of the CWNOAP. Project team leaders work closely with Metro Council representatives on a regular basis to provide residents with information about the purpose, impacts, and work schedules of upcoming projects.