Metro Nashville receives CAP/ER approval

Date added: 01-Mar-2018 07:39 AM

Metro Nashville receives CAP/ER approvalIn late August 2017, the U.S. Environmental Protection Agency (EPA), in conjunction with the Tennessee Department of Environment and Conservation (TDEC), approved the Corrective Action Plan / Engineering Report for Sanitary Sewer Overflows (CAP/ER). The CAP/ER outlines Metro Water Services’ plan to address sanitary sewer overflows (SSOs) in Davidson County and is one of two key pillars of the Clean Water Nashville Overflow Abatement Program.
[read more...]

CWWTP: Gathering neighborhood input

Date added: 01-Mar-2018 07:28 AM

CWWTP: Gathering neighborhood inputOn January 15, 2018, Metro Water Services (MWS) participated in a meeting with residents from the redeveloping neighborhoods of Salemtown and Germantown to discuss the improvements to the nearby Central Wastewater Treatment Plant (CWWTP).
[read more...]

Assessing and rehabilitating manholes

Date added: 01-Mar-2018 07:16 AM

Assessing and rehabilitating manholes During numerous sewer evaluation and rehabilitation projects, the Clean Water Nashville Overflow Abatement Program assesses the condition of manholes to identify...
[read more...]

Plans for CWWTP Expansion

Date added: 01-Sep-2017 02:47 PM

Plans for CWWTP ExpansionMetro Water Services is advancing plans for a major expansion of the Central Wastewater Treatment Plant (CWWTP). The plant was originally constructed in 1958 and has been expanded several times through the years to address environmental quality standards and to meet demands of Nashville’s growth.
[read more...]

Community Engagement

Clean Water Nashville Overflow Abatement Program (CWNOAP) team leaders shared plans for renewing wastewater system infrastructure in North Nashville with over 150 area residents gathered for a February 27 community meeting hosted by Metro Council District 3 representative Brenda Haywood.

District 3, which includes Whites Creek, is one of Nashville’s largest geographic districts. Residents were briefed on current and planned wastewater projects in District3 that include the following:

  • The Annual Rehabilitation FY2014 – Whites Creek Trunk project is currently under construction and consists of rehabilitating approximately 55,800 linear feet of gravity sewer, manholes, and service laterals within the public rights-of-way. This project renews aged infrastructure and addresses downstream overflows by limiting groundwater infiltration.

  • The Brick Church Pike Pipe Improvements project consists of replacing approximately 9,800 linear feet of gravity sewer pipe with larger diameter sewer pipe. Construction is expected to begin in summer 2016 and is scheduled for completion in 2018.

  • The Ewing Creek/Brick Church Equalization Facility consists of constructing a 10.6 million gallon storage tank and an 18 million gallons per day pumping station. The new facility will provide the necessary capacity to eliminate sanitary sewer overflows. Currently in design, the project is scheduled for construction starting in 2017.

The CWNOAP recently completed the Westchester Drive Rehabilitation project, which involved rehabilitating 3,850 feet of sewer pipe along and crossing the North Fork of Ewing Creek, a tributary to Whites Creek. Cracked pipes and other defects within the system that had previously allowed ground water infiltration into the system were repaired.

Community engagement and public information is an ongoing priority of the CWNOAP. Project team leaders work closely with Metro Council representatives on a regular basis to provide residents with information about the purpose, impacts, and work schedules of upcoming projects.