Cleanwater Nashville

Metro Water Services

News

Additional updates

Metro Nashville receives CAP/ER approval

Date added: 01-Mar-2018 07:39 AM

Metro Nashville receives CAP/ER approvalIn late August 2017, the U.S. Environmental Protection Agency (EPA), in conjunction with the Tennessee Department of Environment and Conservation (TDEC), approved the Corrective Action Plan / Engineering Report for Sanitary Sewer Overflows (CAP/ER). The CAP/ER outlines Metro Water Services’ plan to address sanitary sewer overflows (SSOs) in Davidson County and is one of two key pillars of the Clean Water Nashville Overflow Abatement Program.
[read more...]

CWWTP: Gathering neighborhood input

Date added: 01-Mar-2018 07:28 AM

CWWTP: Gathering neighborhood inputOn January 15, 2018, Metro Water Services (MWS) participated in a meeting with residents from the redeveloping neighborhoods of Salemtown and Germantown to discuss the improvements to the nearby Central Wastewater Treatment Plant (CWWTP).
[read more...]

Assessing and rehabilitating manholes

Date added: 01-Mar-2018 07:16 AM

Assessing and rehabilitating manholes During numerous sewer evaluation and rehabilitation projects, the Clean Water Nashville Overflow Abatement Program assesses the condition of manholes to identify...
[read more...]

Plans for CWWTP Expansion

Date added: 01-Sep-2017 02:47 PM

Plans for CWWTP ExpansionMetro Water Services is advancing plans for a major expansion of the Central Wastewater Treatment Plant (CWWTP). The plant was originally constructed in 1958 and has been expanded several times through the years to address environmental quality standards and to meet demands of Nashville’s growth.
[read more...]

Clean Water Nashville OAP begins project work

The Clean Water Nashville Overflow Abatement Program initiated construction on the following major projects in the second quarter of 2012:

  • Expansion of storage capacity at the MWS Driftwood CSO Equalization Facility on Driftwood Street. The facility will be expanded to provide an additional 3 million gallons of storage at the site to reduce combined sewer overflowscombined sewer system conveys both sanitary sewage and stormwater in one piping system. During normal dry weather conditions, sanitary wastewater collected in the combined sewer system is diverted to the wastewater treatment plant before it enters natural waterways. During periods of significant rainfall, the capacity of a combined sewer may be exceeded. When this occurs, excess flow, a mixture of stormwater and sanitary wastewater, is discharged at CSO points, typically to rivers and streams. Release of this excess flow is necessary to prevent flooding in homes, basements, businesses, and streets. into the Cumberland River. The project began in June and will be completed in the first quarter of 2013.
  • Expansion and other improvements to the Dodson Chapel Pumping Station and Equalization Facility, located on MWS property on Panama Drive, including construction of a new storage tank and dry weather pump station, and modification of existing equipment.