Smith Springs Rehabilitation - Area 3 - Harbour Town

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 58,800 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.

Project Details

Project Type: Rehabilitation

View map of project area

Metro Project #: 11-SC-120B

Council District(s): 29,33

Sewer basin: Central

Designer: Civil Infrastructure Associates, LLC

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design June 2017 February 2018
Permitting/Bid/Award February 2018 August 2018
Construction August 2018 October 2019