This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 64,000 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements..

Project Details

Project Type: Rehabilitation

View map of project area

Metro Project #: 11-SC-0120A

Council District(s): 29

Sewer basin: Central

Designer: ICA Engineering

Contractor: Layne Inliner, LLC

Contact Us

Project Timeline

Phase Start Finish
Design February 2015 October 2015
Permitting/Bid/Award October 2015 February 2016
Construction February 2016 March 2017