Shelby Park Rehabilitation - Area 3 - Greenland Avenue

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation of approximately 49,000 linear feet of 8 to 15-inch gravity sewer, 260 associated manholes, and 800 service laterals within Metro's right-of-way and easements.

Project Details

Project Type: Rehabilitation

View map of project area

Metro Project #: 11-SC-0105C

Council District(s): 7

Sewer basin: Central

Designer: Stantec Consulting Services, Inc.

Contractor: Layne Inliner, LLC

Contact Us

Project Timeline

Phase Start Finish
Design December 2013 August 2014
Permitting/Bid/Award August 2014 February 2015
Construction February 2015 July 2016