This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consisted of the evaluation of approximately 54,400 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements. The resulting construction project includes the rehabilitation of approximately 51,000 linear feet of 8 to 12-inch gravity sewer, 300 associated manholes, and 700 service connections.

Project Details

Project Type: Rehabilitation

View map of project area

Metro Project #: 11-SC-0105A

Council District(s): 8

Sewer basin: Central

Designer: RJN Group, Inc.

Contractor: Insituform Technologies, LLC

Contact Us

Project Timeline

Phase Start Finish
Design October 2012 June 2013
Permitting/Bid/Award June 2013 January 2014
Construction January 2014 June 2015