Schrader Equalization Facility

A new 3.2 MG equalization tank with a new 32 mgd wet weather CSO pump station.

Project Details

Project Type: Equalization Facility

View map of project area

Metro Project #: 11-SC-0134

Council District(s): 21

Sewer basin: Central

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design October 2021 November 2022
Permitting/Bid/Award November 2022 May 2023
Construction May 2023 August 2024