Cleanwater Nashville

Metro Water Services

Projects

Schrader Equalization Facility

A new 3.2 MG equalization tank with a new 32 mgd wet weather CSO pump station.

Project Details

Project Type: Equalization Facility

View map of project area

Metro Project #: 11-SC-0134

Council District(s): 21

Sewer basin: Central

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design July 2020 August 2021
Permitting/Bid/Award August 2021 February 2022
Construction February 2022 April 2023

Project Photos