This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consisted of the evaluation of approximately 31,400 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements. The resulting construction project includes the rehabilitation of approximately 22,000 linear feet of 8 to 18-inch gravity sewer, 110 associated manholes, and 250 service connections.

Project Details

Project Type: Rehabilitation

View map of project area

Metro Project #: 11-SC-0106

Council District(s): 9

Sewer basin: Dry Creek

Designer: Cardozo Engineering, Inc.

Contractor: Insituform Technologies, LLC

Contact Us

Project Timeline

Phase Start Finish
Design September 2012 June 2013
Permitting/Bid/Award June 2013 December 2013
Construction December 2013 February 2015