Mill Creek / Opryland Equalization Facility - Phase II

This project increased the storage capacity of the existing equalization facility through the construction of a 19 million gallon pre-stressed concrete tank that was constructed adjacent to the existing 15 million gallon tank. The storage tanks are utilized when sewer flows exceed the capacity of the existing sewer system. The peak flows are stored until the flows in the system recede, and the stored volume can be conveyed through the system to treatment. Without the construction of this facility, flows in excess of the system capacity resulted in sanitary sewer overflows.

Project Details

Project Type: Equalization Facility

View map of project area

Metro Project #: 11-SC-0102

Council District(s): 19

Sewer basin: Central

Designer: URS Corporation

Contractor: Cumberland Valley Constructors, Inc.

Contact Us

Project Timeline

Phase Start Finish
Design August 2012 May 2013
Permitting/Bid/Award May 2013 January 2014
Construction January 2014 May 2015