Cleanwater Nashville

Metro Water Services

Projects

Lakewood Rehabilitation – Area 2 – Old Hickory

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 52,500 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.

Project Details

Project Type: Rehabilitation

View map of project area

Metro Project #: 11-SC-0153

Council District(s): 11

Sewer basin: Dry Creek

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design October 2019 April 2020
Permitting/Bid/Award April 2020 October 2020
Construction October 2020 February 2022

Project Photos