Hurricane Creek Pipe Improvements

In order to provide increased conveyance capacity and address existing restrictions within the sewer system, approximately 12,100 linear feet of gravity sewer pipe will be replaced with larger sewers.

Project Details

Project Type: Conveyance

View map of project area

Metro Project #: 11-SC-0116

Council District(s): 33

Sewer basin: Central

Designer: HDR Engineering

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design July 2016 June 2018
Permitting/Bid/Award June 2018 November 2018
Construction November 2018 August 2020