Highway 100 / Tyne Boulevard Pipe Improvements

To provide increased conveyance capacity and address restrictions within the sewer system that result in overflows, approximately 17,900 linear feet of gravity sewer pipe will be replaced with larger sewers.

Project Details

Project Type: Conveyance

View map of project area

Metro Project #: 11-SC-0147

Council District(s):

Sewer basin:

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design April 2023 October 2024
Permitting/Bid/Award October 2024 January 2026
Construction January 2026 February 2028