Cowan Street Pump Station Upgrades

In order to convey additional flows and remediate nearby sanitary sewer overflows, this project includes a new 15 million gallon per day pump station and the upgrade of a portion of the associated force main.

Project Details

Project Type: Conveyance

View map of project area

Metro Project #: 11-SC-0114

Council District(s):

Sewer basin:

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design April 2019 January 2020
Permitting/Bid/Award January 2020 October 2020
Construction October 2020 December 2021