Cleanwater Nashville

Metro Water Services

Projects

Cowan Street Pipe Improvements

Approximately 7,300 linear feet of gravity pipe replacement, increasing diameters ranging from 10 inches to 30 inches to a range of 12 inches to 36 inches.

Project Details

Project Type: Conveyance

View map of project area

Metro Project #: 11-SC-0113

Council District(s): 2,5

Sewer basin: Central

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design May 2019 July 2019
Permitting/Bid/Award July 2019 February 2021
Construction February 2021 June 2022

Project Photos