Cowan Street Pipe Improvements

Approximately 7,300 linear feet of gravity pipe replacement, increasing diameters ranging from 10 inches to 30 inches to a range of 12 inches to 36 inches.

Project Details

Project Type: Conveyance

View map of project area

Metro Project #: 11-SC-0113

Council District(s): 2,5

Sewer basin: Central

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design January 2021 January 2022
Permitting/Bid/Award January 2022 March 2023
Construction March 2023 July 2024