Cleeces Ferry – Area 1 – Summerly Drive

This project was developed to renew aging infrastructure and address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 52,600 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.

Project Details

Project Type: Rehabilitation

View map of project area

Metro Project #: 11-SC-0145

Council District(s): 20,23,24

Sewer basin: Whites Creek

Designer:

Contractor:

Contact Us

Project Timeline

Phase Start Finish
Design May 2019 October 2019
Permitting/Bid/Award October 2019 January 2020
Construction January 2020 August 2021